The Refractory RFQ Brief: Give Suppliers the Conditions That Matter
A concise refractory enquiry should connect equipment, zone, exposure, geometry, installation, quantity, documents, and deadline.

"Please quote refractory for a furnace" starts a conversation, but it is not enough information for a dependable recommendation. Even a known grade can be misapplied if the service, shape, installation method, or delivery window has changed. A short technical brief helps suppliers respond on the same basis and makes their offers easier to compare.
The brief does not need to be a long report. It needs to answer the questions that change material selection and supply.
Name the equipment and zone
State the furnace or vessel type and the exact location: wall, roof, floor, burner opening, trough, door, or backup layer. Include a drawing, photograph, or marked sketch. The same equipment can contain several lining zones with different wear and temperature patterns.
Describe the existing lining and what failed. If the project is a first installation, provide the proposed cross-section and the design responsibility. Do not treat a previous grade as automatically approved for a changed process.
Describe actual service
Provide normal and peak temperatures, cycling, atmosphere, process chemistry, contact with slag or metal where applicable, abrasion, impact, and any known hot spots. Separate measured values from estimates. If a value is unknown, say so rather than filling the gap with a guess.
Explain the failure mechanism suspected and attach inspection evidence. Suppliers can then ask targeted follow-up questions or identify where a product data sheet does not answer the design problem.
Define the supply and installation basis
List shapes, drawings, dimensions, required quantity, packing needs, destination, and delivery date. State whether the material will be cast, rammed, gunned, laid as brickwork, or installed as a precast component. Include the available cure and dry-out window where relevant.
Identify documents needed with the offer or delivery, such as a current technical datasheet, safety information, quality records, or drawing approval. Make clear who approves substitutions and whether a trial or sample is required.
Better enquiries reduce hidden assumptions before they become site problems.
Compare offers against the same brief
Review proposed grade, property basis, installation requirements, exclusions, packing, and delivery commitment together. A lower material price can be outweighed by an unsuitable method or missed outage window. Ask suppliers to state any assumptions and deviations explicitly.
Use the brief as a comparison sheet
Create a line for each proposed product or shape and record the supplier's stated grade, governing datasheet revision, packing, installation method, lead time, and deviations. Separate confirmed facts from assumptions. If two offers use different thicknesses or forms, ask for clarification before ranking their prices. The cheapest line item may not describe the same scope.
Include a small decision log. Record why the selected grade addresses the zone's wear and temperature conditions, who approved the choice, and what must be verified at delivery or installation. This makes the procurement decision useful to operations and maintenance, not only to purchasing.
After installation, keep the final brief with the as-built record. At the next outage, compare actual wear with the assumptions written at enquiry stage. That feedback can improve the next specification and reduce repeated requests for the same missing information. A good RFQ becomes the first page of the lining's service history.
When a supplier asks for missing information, update the master brief and share the same clarification with every bidder. This keeps comparisons fair and avoids a situation where different offers solve different versions of the job. Record the final revision used for approval and purchase.
Include a contact for technical questions so a supplier can resolve uncertainty before pricing.
Royal's product catalogue can help identify candidate grades. Send the completed brief and drawings for a project-specific response.